Consultations

TN3-2026-009

Shore Road culvert replacement

Replacement of the failed culvert at the Shore Road crossing. Survey completed, no historic properties affected, work proceeding with a monitor on site.

Consultation closed 17 July with a finding of no historic properties affected.

The Historic Preservation Office completed a survey of the crossing in June. No cultural resources were identified within the area of potential effect.

The Nation agreed to the finding on the condition that a monitor is present during excavation, which the agency accepted. Work begins 24 August.

This is what a straightforward consultation looks like. Most of them are.